Build log 2025

Eleven weeks from drain to boat.

  1. Week 23Drainage and manhole laid, groundworks finished on 6 June.
  2. Week 24Crane and scaffolding, timber delivered, walls raised. On 13 June the boathouse stands.
  3. Week 25Topping-out on 18 June. Roof sealing, preparing the green roof, electrics begin.
  4. Week 26Sheet metal work, green roof, rails for the sliding doors.
  5. Week 27Sliding doors fitted, façade, four vents.
  6. Week 28Façade finished.
  7. Week 29 to 31Building finished, interior cleaned.
  8. 2 AugustAll boats move into the boathouse, still on the old racks. A milestone.
The larch façade with scaffolding during construction
Members in the shell at the topping-out party
The green roof of the boathouse

Crowdfunding

A piece of the boathouse is yours.

By taking on a building part you help pay for the boathouse. If you like, your name goes on the sponsor wall. Anyone can take part, members or not.

A wooden board

€ 50

A wooden post

€ 250

A wooden beam

€ 500

Donations to the club are tax deductible in Austria under the tax office notice of 18 June 2025 (registration number SP-30389). Several and different pieces are possible.

From groundbreaking to moving in

Design mit Seele.Herzhaus Studios